Gas Pressure Control, Metering, and Delivery Station (SRMP) for SC Chimcomplex S.A. Borzești – Râmnicu Vâlcea Branch
SUTECH successfully completed a key project for SC Chimcomplex S.A. Borzești, Râmnicu Vâlcea branch, consisting in the construction of the “Gas Connection and SRMP for Chimcomplex Râmnicu Vâlcea” objective. The project contributes to the modernization of the energy infrastructure of the industrial platform.
Scope of work:
- Installation of a Ø 16”, PN 40 natural gas pipeline, approximately 0.8 km in length, connected to the Schitu-Golești – Drăgășani main transmission pipeline
- Construction of gas Pressure Control, Metering, and Delivery Station (SRMP) with a nominal pressure of 40 bar and a technical capacity of 36,000 Smc/h, configured with one inlet and four outlets at different pressure levels
- Installation of four distribution pipelines to ensure gas delivery for multiple on-site industrial applications
Project impact:
This strategic investment supports the sustainable development of Romania’s industrial sector by aligning the energy infrastructure of SC Chimcomplex with European standards and ensuring a safe and efficient gas supply for technological processes.